Sunday, July 6, 2014

PMP Formulae

PMP FORMULAE

Please feel free to download the pdf file of PMP formulae at this link  

EARNED VALUE
SIGMA
CV=EV-AC
CPI=CV/AC
SV=EV-PV
SPI=EV/PV
1 sigma = 68.26%
EAC (no variances) = BAC/CPI
ETC=EAC-AC
2 sigma = 95.46%
EAC (fundamentally flawed)=AC+ETC
ETC(flawed)=new estimate
3 sigma = 99.73%
EAC (atypical) = AC+BAC-EV
ETC(atypical)=BAC-EV
6 sigma = 99.99%
EAC (typical)=AC+((BAC-EV)/CPI)
ETC(typical)= (BAC-EV)/CPI
PROCUREMENT
Percent complete=(EV/BAC)*100
% Spent=(AC/BAC)*100
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost
EV=%complete*BAC
VAC=BAC-EAC
CV%=(CV/EV)*100
SV%=(SV/PV)*100
Based on BAC:
TCPI = (BAC - EV) / (BAC - AC)
Based on EAC:
TCPI = (BAC - EV) / (EAC - AC)

PERT
CLASSES OF ESTIMATES
PERT 3-point estimate=(tP+4tML+tO)/6
PERT a-estimate=(tP-tO)/6
Order of magnitude estimate =
-25% to +75%
PERT activity variance=[(tP-tO)/6]2
Triangular estimate = (tP+tML+tO)/3
PERT Variance all activities = Sum=[(tP-tO)/6]2
Preliminary estimate=
-15% to +50%
PROJECT SELECTION
PV=FV/(1+r)n
FV=PV * (1+r)n
NPV=Select biggest number
Budget estimate= -10% to +25%
ROI=Select biggest number
IRR=Select biggest number
Final estimate = 0%
Payback period = Add projected cash inflows minus expenses until you reach the initial investment
BCR=Benefit/Cost.
BCR < 1 is bad;   BCR > 1 is good.
The project with the bigger BCR is the better one.
CBR = Cost/Benefit;  CBR > 1 is bad; CBR < 1 is good. The project with the smaller CBR is the better one.
Opportunity Cost = The value of the project not chosen
Exp. Value = Probability % * Consequence $
Communication checklist = [n (n-1)]/2
EMV = Probability * Impact in currency
DEPRECIATION
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
IMPORTANT VALUES
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; less than the control limits
Float on the critical path = 0 days
Pareto Diagram = 80/20

Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%)
NETWORK DIAGRAM
Forward Pass
ES = EF of the predecessor node
EF = ES + Dur

ES       Dur     EF
          
         Node

LS      Float    LF
Backward Pass
LF = LS of the Successor
LS = LF – Dur
Slack = LF – EF = LS ES
Free Float = ES(Successor) - EF(Predecessor)

If you liked this article please leave your comments in the comments box. It will inspire me to write more articles like this.  

No comments:

Post a Comment